Valley of the Moon Children’s Home Building Project – Facts at a Glance
Phase I (Site Work)
Phase II (Home and Kitchen)
Cost for Phase I and Phase II - $11.1 million – VMCF contribution - $2.6 million
Phase III (Site Work, Redwood Children’s Center, Medical/Dental/Mental Health, Baby/Toddler Area, Admissions, Visiting, Children Support Services, Administration and Volunteer Offices
Cost for Phase III - $14.1 million – VMCF contribution - $3 million
TOTAL PROJECT COST - $25.2 million – VMCF contribution total - $5.6 million
Valley of the Moon Children’s Foundation - Project Timeline
-
November 1999 – Toy Story II – Movie Premier Fundraising Event (raised over $200,000)
-
October 2001 – Monsters, Inc. – Movie Premier Fundraising Event (raised over $400,000)
-
June 2003 – Start of site work – Phase I
-
June 2003 – Groundbreaking for Phase II
-
September 2003 – Foundation contributed $1,800,000 to County for Phase II
-
November 2003 – Start of Phase II construction (children’s housing, kitchen, and dining room)
-
December 2003 – Helping Hand Series in Press Democrat (raised over $200,000)
-
April 2004 – Foundation contributed $6,000 to County for Redwood Children’s Center (specialized equipment and furniture needs)
-
March 2005 – Foundation contributed $801,898 to County for full, professional kitchen for Valley of the Moon Children’s Home (Phase II kitchen and dining area)
-
May 2005 – Completion of Phase II construction
-
May 2005 – Dedication of Phase II
-
May 2005 – Foundation contributed $200,000 to County to cover the cost of plan update for Phase III
-
June 2005 – Children moved into new Valley of the Moon Children’s Home
-
March 2007 – Foundation contributed $1,000,000 to County for Phase III (first of three)
-
October 2007 – Groundbreaking for Phase III
-
October 2007 – Start of Phase III construction
-
October 2007 – Foundation contributed $1,000,000 to County for Phase III (second of three)
-
March 2008 – Foundation received $200,000 grant from Sonoma Paradiso Foundation
-
December 2008 – Foundation contributed $800,000 to County for Phase III (third and final of commitment)
-
March 2009 – Completion and Dedication of Phase III